Plans to improve the Little Red River Park Toboggan Hill have been pushed into next year after Prince Albert city council authorized the cancellation of a $122,066 construction purchase order Monday night.
The work was awarded to Snake Lake Construction Ltd. in July and included an accessible walking path, clay and topsoil work, grading, compaction, seeding and cedar fencing.
A City report said the contractor is unable to complete the work during the 2026 construction season. Administration will retender the project in spring 2027.
Coun. Darren Solomon said he understood why the work could not be completed this year and supported delaying the project.
“There’s been tremendous work done out there,” Solomon said. “I do look forward to the upgrades next year, and I do think this is the right thing to do, is to delay the purchase order and send it for retender.”
The original purchase order was for $109,969.50 plus taxes, bringing the total project value to $122,066.15.
Most of that cost was to be covered by a $100,000 contribution from the Rotary Club of Prince Albert generated through its 2025 Lobsterfest fundraiser. Administration will work with Rotary to confirm that the money remains designated for the project in 2027.
The City said the old price will not be used as the basis for next year’s project. A new tender will seek current market pricing, meaning the final cost could change.
Coun. Blake Edwards asked whether Snake Lake would be willing to honour its 2026 price next year.
Parks and Open Spaces Manager Tim Yeaman said the City discussed the issue with the company, but purchasing requirements mean the work has to be retendered.
“If he’s in a position to rebid on that tender next year, he certainly will,” Yeaman said.
The delay affects what the City has described as Phase One of the Toboggan Hill project. It does not, on paper, cancel a separately approved second phase that includes snowmaking equipment and other amenities.
Council approved Phase Two in August using a separate $100,000 contribution from the Malcom Jenkis Family Foundation.
The plan includes the purchase of and SMI Super Polecat Snowmaker for $56,750 plus taxes, $12,000 for recognition signage, $10,000 for picnic tables, waste receptacles and other amenities, and $2,500 for security cameras. The City was also working with SOS Electric Ltd. on donated lighting components and installation.
The snowmaker is intended to supplement natural snowfall, help establish a more reliable snow base and potentially extend the operating season.
The August report said Phase Two was targeted for completion before the 2027-2 winter season and described it as building on the physical improvements completed through Phase One.
Monday’s cancellation report does not say the snowmaker or Phase Two have been cancelled. It also does not say whether pushing the Phase One construction into 2027 will affect the Phase Two schedule.
The city said the existing conditions at the hill will continue to be managed through regular Parks and Open Spaces operations until the delayed work can proceed.