Prince Albert’s long-running plans for additional fire stations took another step forward Monday as Executive Committee backed a $20,000 feasibility study for consideration during the City’s 2027 budget deliberations.
The Phase 1 pre-design study would examine operational needs, potential station locations, response coverage, future growth, preliminary building layouts, costs, timelines and possible procurement options.
Fire Chief Kris Olsen told councillors the City should complete that work before deciding whether to purchase or adapt an existing prototype fire station design.
“Before considering any design purchase, we need to confirm fundamental questions such as where future stations should be located, what operational requirements must be met, how they support current and future service demands, and what levels of investment will be required,” Olsen said.
Council had directed administration in May to investigate whether purchasing a prototype design, including adaptation and reuse rights, could reduce the cost and time required to eventually build new stations. Administration came back recommending the feasibility work first.
The study is expected to take about 10 to 12 weeks once authorized.
Coun. Bryce Laewetz said he supports expanding fire services, but questioned how long the study would remain useful if construction is still several years away. Olsen said factors such as future development and changes in the City’s growth pattern could affect that.
Coun. Tony Head questioned spending $20,000 on an outside consultant, arguing that much of the necessary expertise already exists within the Fire Department and City administration.
“I think we have the capacity internally and the expertise of yourself and others within the fire department to come up with what’s best laid plans,” Head told Olsen.

Arjun Pillai/Daily Herald
Coun. Dawn Kilmer speaks during Monday’s Executive Committee meeting at Prince Albert City Hall, where she supported moving ahead with the proposed fire station feasibility study.
Olsen said some of the work, including previous GIS analysis identifying suitable station locations, has already been completed. However, he said a Phase 1 study also covers matters such as utilities, geotechnical conditions, grading, traffic and emergency-response requirements that are standard parts of preparing a building project.
Acting Community Development Director Michael Nelson told council that a later Phase 2 would involve detailed architectural, structural, mechanical and electrical drawings. He estimated that process could take 12 to 18 months, followed by roughly 18 months of construction if funding was in place.
Mayor Bill Powalinsky initially questioned whether the study was being undertaken too soon, noting that construction could still be years away and cost estimates could change significantly.
He later said he was prepared to support the motion, particularly because the study would provide information about site suitability, utilities, access and other physical requirements.
Coun. Dawn Kilmer said completing the study now would give council better information when deciding how and when to finance a future station.
“If we put it on the back burner, don’t work from a place of knowing, we will be in 10 years talking about the same thing,” Kilmer said.
The issue has been studied for decades. City reports dating back to 1985 have called for additional stations, while a 2008 master plan recommended one additional station within five years and a third within 10 years. City-owned land has since been identified on 15th Avenue East and 28th Street West for potential future stations.
Executive Committee’s recommendation will go forward as part of the 2027 budget process. The $20,000 would come from the Protective Services New Facility Reserve.